Timetable

 

The Ministry has revised the timetable for the Managed Spectrum Park, having considered the views received by industry. This is to afford applicants more time to develop their business plans and secure investment funding.

The current revised timetable is given below.

 

Design
Decisions and announcements
September 2008

Drafting of Final rules

Preparation and review
October 2008
Implementation
Invite applications

March 2009

Applications close
September 2009
Ministry appoints ARE contractor
October 2009

Applicants advised of outcome of high level analysis by ARE contractor

November 2009

Issue initial licences

December 2009

 