The Ministry has revised the timetable for the Managed Spectrum Park, having considered the views received by industry. This is to afford applicants more time to develop their business plans and secure investment funding.
The current revised timetable is given below.
Design | |
Decisions and announcements | September 2008 |
Drafting of Final rules | |
Preparation and review | October 2008 |
Implementation | |
Invite applications | March 2009 |
Applications close | September 2009 |
Ministry appoints ARE contractor | October 2009 |
Applicants advised of outcome of high level analysis by ARE contractor | November 2009 |
Issue initial licences | December 2009 |